MAJOR

A request has been submitted to install a combination boatlift/PWC lift includes 15.5” x 20’ aluminum catwalk into existing slip onto existing poles channelward 20’. The site of the proposed construction is described as being located at 201 Windward Drive, Unit 1, Parcel # 3838A--0 -0116-131898 in the Town of Ocean City, MD
Applicant: Ocean City Boatlifts & Marine Construction, Inc.
Owner: Traci & Perry Toskov PW14-068

A request has been submitted to replace 531’ of bulkhead within 18” of existing wood bulkhead on west and north side with 13’ of replacement bulkhead on southeast end in front of storm drains to be extended. 17 new finger piers 10’ x 3’ along south side in existing slips. 531’ of landward walkway 3’ wide from new bulkhead back over old. The site of the proposed construction is described as being located at 120 53rd ST Parcel # 6759-1-3 -0113- in the Town of Ocean City, MD
Applicant: Just-Rite Marine Structures, Inc.
Owner: Bay Spot Condo PW14-069

A request has been submitted to install one beamless boatlift, 13’ x 10’ “Magnum S” or approved equal by engineer. This project proposes no new piles, and no channelward encroachment. The site of the proposed construction is described as being located at 778 94th Street, Unit 104- Slip P-2 Parcel # 9647-2-0-0115-398916 in the Town of Ocean City, MD
Applicant: Carpenter Engineering, LLC
Owner: Leonard J. Reeder PW14-073

MINOR

A request has been submitted to install 140’ of new vinyl replacement batter pole bulkhead for a maximum channelward extension of 1.5’. The site of the proposed construction is described as being located at 4709 Coastal Hwy Parcel # 6874-3 – 113 - in the Town of Ocean City, MD
Applicant: Hidden Oak Farm, LLC
Owner: Wight Bay Condo Association PW14-070

A request has been submitted to remove stringers, headers & decking on existing 5’x 40’ parallel platform (leaving pilings in place), to install 52’ of replacement vinyl bulkhead w/batter pile anchor system 18” channelward of existing bulkhead and install new stringers, headers, decking on existing piles (raising bulkhead height and set of steps on pier). (Note: Flares on pier to be removed-not to code). The site of the proposed construction is described as being located at 602 Gulfstream DR Parcel # 8020A-1487B-7A-0 -0117-194458 in the Town of Ocean City, MD
Applicant: Ocean Services of DE, Inc. c/o Erin Rogers
Owner: Thomas & Rosalie ByronPW14-071

A request has been submitted to replace 100’+ of bulkhead & walkways. The site of the proposed construction is described as being located at 2501 Philadelphia Ave Parcel # 5754 -7-76N-0 -0111-045754 in the Town of Ocean City, MD
Applicant: 25th Street Development
Owner: 25th Street Development PW14-072
Emergency Permit #27080 issued